Progress
|
Element of the scheme |
Completion Date Planned |
Completion Date Achieved |
|---|---|---|
|
A66 Eastbound Improvements Summer 2008 to Winter 2009
Erect new signage on existing footbridges Repair Existing Bridge parapets |
30/11/09 Feb 2010 |
30/11/09 10/02/10 |
|
A66 Westbound Improvements Summer 2008 to Spring 2009
Erect new signage on existing footbridges Replace Existing Bridge parapets Remove Traffic Management |
30/11/09 Feb 2010 18/02/10 |
30/11/09 15/02/10 18/02/10 |
|
A66 Central Reservation Winter 2009 to Summer 2009 ALL WORKS COMPLETE |
June 2009 |
15/06/09 |
|
Newport Roundabout & Link Road Summer 2008 to Spring 2010 Open new link road Final landscaping Complete lighting column works |
25/11/09 18/12/09 26/03/10 |
25/11/09 17/12/09
|
|
|
|
|
|
|
|
|
|
Riverside Link Rail Bridge Construction ALL WORKS COMPLETE |
July 2009 |
24/07/09 |
|
|
|
|
|
North Roundabout Summer 2008 to Autumn 2009
Complete white lining for link road opening |
19/11/09 |
18/11/09 |
|
|
|
|