Progress

Element of the scheme

Completion Date

Planned

Completion Date

Achieved

A66 Eastbound Improvements

Summer 2008 to Winter 2009

 

Erect new signage on existing footbridges

Repair Existing Bridge parapets

 

 

 

30/11/09

Feb 2010

 

 

 

30/11/09

10/02/10

A66 Westbound Improvements

Summer 2008 to Spring 2009

 

Erect new signage on existing footbridges

Replace Existing Bridge parapets

Remove Traffic Management

 

 

 

30/11/09

Feb 2010

18/02/10

 

 

 

30/11/09

15/02/10

18/02/10

A66 Central Reservation

Winter 2009 to Summer 2009

ALL WORKS COMPLETE

 

 

 June 2009

 

 

15/06/09

Newport Roundabout & Link Road

Summer 2008 to Spring 2010 

Open new link road

Final landscaping

Complete lighting column works

 

 

25/11/09

18/12/09

26/03/10

 

 

25/11/09

17/12/09

 

 
 

 

 

 

 

Riverside Link Rail Bridge Construction

ALL WORKS COMPLETE

 

July 2009

 

24/07/09

 

 

 

North Roundabout

Summer 2008 to Autumn 2009

 

Complete white lining for link road opening

 

 

 

19/11/09

 

 

 

18/11/09

 

 

 

Document Actions